Identify required effort to complete database migration as indicated by AWS SCT

publish date2024/09/11 02:20:10.240225 UTC

volume_mute

The assessment report shows you what AWS SCT can convert automatically, which objects need manual remediation, and which objects require significant remediation. Levels of effort are color coded as green, gray, orange, and red in the summary report.

  •   (1) transparent
     
  •   (2) transparent
     
  •   (3) transparent
     
  •   (4) transparent
     
Please drag and drop the selected option in the right place or type it instead
Objects automatically converted
Objects with complex actions
Objects with medium-complexity actions
Objects with simple actions

Correct Answer

(1) Objects automatically converted
(2) Objects with simple actions
(3) Objects with medium-complexity actions
(4) Objects with complex actions

Explanation

Simple actions usually require less than an hour, medium actions can be completed in 1-4 hours, and complex actions would typically take over 4 hours. You can use this information to develop level-of-effort estimates across different lines of responsibility like database administrators (DBAs), application developers, test engineers, and business stakeholders.

Reference