A solutions architect intends to conduct an AWS Well-Architected Framework Review for a workload that is scheduled to go live soon. A key stakeholder emails to explain that the team is too busy to dedicate time for the review because they are working on a tight timeline before the launch. Which is the best response?

publish date2024/09/10 00:51:53.014355 UTC

volume_mute

Correct Answer

Explain that it is better to understand potential issues before the launch. Even though they may not be able to implement all changes before going live, it will help the team create an action plan for the future