A team finds a few high-risk issues and medium-risk issues identified in their Improvement Plan. What should they do with this information?

publish date2024/09/10 00:58:46.951802 UTC

volume_mute
Create a chart or list of all high-risk issues and medium-risk issues to help prioritize a starting point
Fire the engineer who built part of the workload that has a high-risk issue
Send a company-wide email explaining that they need all hands on deck to fix the identified issues
Pause the entire launch plan

Correct Answer

Create a chart or list of all high-risk issues and medium-risk issues to help prioritize a starting point

Explanation

Treat risk like data points, first collecting them and then prioritizing what is most important based on a set of criteria. The criteria are the business outcomes for a workload. By reviewing business outcomes and risk, it is possible to identify which risk should be addressed first.