What is the product backlog in Scrum, and what happens to it during the assessment phase of a sprint?

Correct Answer

The product backlog is the list of work to be done on the project; during the assessment phase it is reviewed, priorities and risks are assigned, and the customer can introduce new requirements or tasks at the beginning of each sprint

Explanation

The product backlog is the list of work to be done on the project. During the assessment phase of each sprint, this is reviewed and priorities and risks are assigned. The customer is closely involved and can introduce new requirements or tasks at the beginning of each sprint.

Reference

Software Engineering, Ian Sommerville, 9th edition