During the development stage of a Scrum sprint, how is the team managed in terms of external contact?

Correct Answer

The team is isolated from the customer and organisation with all communications channelled through the Scrum master — the Scrum master's role is to protect the development team from external distractions

Explanation

During the development stage, the team is isolated from the customer and the organisation, with all communications channelled through the Scrum master. The role of the Scrum master is to protect the development team from external distractions.

Reference

Software Engineering, Ian Sommerville, 9th edition