Can Plan-driven Support Incremental Delivery?

publish date2026/06/04 04:42:31.651909 UTC

volume_mute

True or False: A plan-driven software process cannot support incremental development and delivery.

Correct Answer

False

Explanation

False. A plan-driven software process can support incremental development and delivery. It is perfectly feasible to allocate requirements and plan the design and development phase as a series of increments. Equally, an agile process is not inevitably code-focused and may produce some design documentation.

Reference

Software Engineering, Ian Sommerville, 9th edition