What is the ultimate concern that should drive software development, regardless of whether a project is labelled plan-driven or agile?
Correct Answer
Whether the buyers of the software have an executable software system that meets their needs and does useful things for the individual user or the organisation
Explanation
The issue of whether a project can be labelled as plan-driven or agile is not very important. Ultimately, the primary concern of buyers of a software system is whether or not they have an executable software system that meets their needs and does useful things for the individual user or the organisation. In practice, many companies who claim to use agile methods have adopted some agile practices and integrated these with their plan-driven processes.
Reference
Software Engineering, Ian Sommerville, 9th edition