Scrum — Sprint and Scrum Master
publish date: 2026/06/04 20:56:22.705234 UTC
The diagram below shows the Scrum process.
Complete the sentences.
A Scrum sprint is a fixed-length planning unit, normally (1) weeks, in which features are selected and software is developed. All communications during the sprint are channelled through the (2), whose role is to protect the development team from external distractions.
Please drag and drop the selected option in the right place or type it instead
2–4
Scrum master
3-4
Project Manager
Correct Answer
(1) 2–4
(2) Scrum master
Explanation
A Scrum sprint is normally 2–4 weeks long. During the development stage, the team is isolated from the customer and organisation with all communications channelled through the Scrum master, whose role is to protect the development team from external distractions.
Reference
Software Engineering, Ian Sommerville, 9th edition