Who should be involved in a requirements review? Which groups should participate? Select all that apply.

Correct Answer

(1) Customer representatives who can validate the requirements reflect their actual needs
(2) System engineers who will implement the system
(3) System test engineers who will develop validation tests
(4) The requirements engineer who wrote the document
(5) System maintenance engineers who will maintain the system

Explanation

Requirements reviews should include all key stakeholder groups: customer representatives (to validate needs), system engineers (to check implementability), test engineers (to check testability), the requirements engineer (to clarify intent), and maintenance engineers (to check long-term maintainability). External marketing consultants without project knowledge would not contribute meaningfully.

Reference

Software Engineering, Ian Sommerville, 9th edition