A BA is working on a project where the requirements are expected to remain stable for a long period. The organization prefers to have all requirements signed off before any development begins. Which planning approach is most suitable?

publish date2026/03/06 08:02:37.461413 UTC

volume_mute

Correct Answer

Predictive

Explanation

A predictive (waterfall) approach is best when requirements are stable and upfront planning is required.