In the middle of a project, the Lead BA receives a formal request to add a new set of requirements that were previously out of scope. The project is already in the design phase. What is the BA's immediate next step?https://go-math-science.com/computing/software-engineering/requirements-engineering/cbap-certification-practice-exams/cbap-practice-exam-1/in-the-middle-of-a-project-the-lead-ba-receives-a-formal-request-to-add-a-new-set-of-requirements-that-were-previously-out-of-scope-the-project-is-already-in-the-design-phase-what-is-the-bas-immediate-next-stephttps://go-math-science.com/@@site-logo/logo-new.png
volume_mute
In the middle of a project, the Lead BA receives a formal request to add a new set of requirements that were previously out of scope. The project is already in the design phase. What is the BA's immediate next step?
publish date: 2026/03/04 12:19:31.821659 UTC
volume_mute
Correct Answer
Assess the impact of the proposed change
Explanation
Correct Answer: Assess the impact of the proposed change
The BA must first determine how the new requirements affect the existing schedule, budget, and scope before any action is taken.