In the middle of a project, the Lead BA receives a formal request to add a new set of requirements that were previously out of scope. The project is already in the design phase. What is the BA's immediate next step?

publish date2026/03/04 12:19:31.821659 UTC

volume_mute

Correct Answer

Assess the impact  of the proposed change

Explanation

Correct Answer: Assess the impact of the proposed change

The BA must first determine how the new requirements affect the existing schedule, budget, and scope before any action is taken.