While defining the future state for a new software implementation, the BA identifies that the end-users lack the technical skills to use the new system. This represents a risk. What is the BA's primary goal in the 'Assess Risks' task?

publish date2026/03/05 12:24:33.158288 UTC

volume_mute

Correct Answer

To understand the probability and impact of the risk

Explanation

Assessing risk involves determining the likelhood of occurrence and the severity of the consequences to value realization.