A BA is determining whether to use a 'Predictive' or 'Adaptive' approach for a new initiative. Which factor is MOST influential in this decision?
publish date: 2026/04/27 21:14:50.229201 UTC
volume_mute
Correct Answer
The level of uncertainty and the frequency of change in the project environment.
Explanation
Predictive approaches work best when requirements are well-defined and stable, whereas Adaptive (Agile) approaches are necessary when there is high uncertainty and a need for iterative refinement.