A BA is using a 'RACI' matrix to plan stakeholder engagement. What does the 'R' stand for?

publish date2026/04/27 21:14:54.193868 UTC

volume_mute

Correct Answer

Responsible

Explanation

In a RACI matrix, 'Responsible' identifies the person who actually performs the work.