The BA is planning how to handle 'Traceability' in a project with over 2,000 requirements. What should they prioritize?
publish date: 2026/04/27 21:14:52.193093 UTC
volume_mute
Correct Answer
Identify the value that traceability provides vs. the effort required to maintain it.
Explanation
The level of traceability is a planning decision based on project complexity, risk, and regulatory requirements. It must be balanced against the effort to maintain it.