The BA is planning how to handle 'Traceability' in a project with over 2,000 requirements. What should they prioritize?

publish date2026/04/27 21:14:52.193093 UTC

volume_mute

Correct Answer

Identify the value that traceability provides vs. the effort required to maintain it.

Explanation

The level of traceability is a planning decision based on project complexity, risk, and regulatory requirements. It must be balanced against the effort to maintain it.