Which technique is BEST for estimating the effort required for BA activities by comparing them to similar tasks in previous projects?

publish date2026/04/27 21:14:53.313057 UTC

volume_mute

Correct Answer

Analogous Estimation.

Explanation

Analogous estimation uses historical data from similar initiatives to provide a high-level estimate of effort.