volume_mute

If the BA decides to re-sequence the process so the 'Permit Application' is filed *before* the 'Technical Survey,' what is the primary risk?

publish date1969/12/31 00:00:00 UTC

volume_mute

Correct Answer

The company may pay permit fees for a house that ultimately fails the technical survey (7% risk).

Explanation

Decision-making in process design involves 'Trade-offs.' Re-sequencing tasks to run in parallel can shorten the 110-day cycle, but it introduces 'Financial Risk' (sunk costs in permit fees for failed sites). This relates to the 'Strategy Analysis' domain task of 'Assess Risks,' which involves understanding the uncertainties that may impact the value of a change strategy.

Reference

go-math-science.com


Quizzes you can take where this question appears