What should a BA do if elicitation results are found to be inconsistent across different stakeholders?

publish date1969/12/31 00:00:00 UTC

volume_mute

Correct Answer

Facilitate a collaboration session to resolve the contradictions.

Explanation

Resolving inconsistencies is a key part of collaboration; the BA must help stakeholders reach a consensus or clarify the business need.