What should the BA do if a key stakeholder is consistently absent from elicitation sessions?
publish date: 1969/12/31 00:00:00 UTC
volume_mute
Correct Answer
Work with the Project Manager to identify the cause and improve engagement.
Explanation
Managing collaboration is proactive. You must find out 'why' they are absent (lack of time, lack of interest, fear) and solve the root cause.