Which of the following is a risk if a BA skips 'Confirm Elicitation Results'?

publish date1969/12/31 00:00:00 UTC

volume_mute

Correct Answer

The requirements may be based on a misunderstanding of stakeholder input.

Explanation

Confirmation is the quality check for elicitation. Without it, you may analyze and build based on incorrect or misinterpreted information.