A project sponsor demands that a new feature be added to a baselined project. What should the BA do FIRST?
publish date: 1969/12/31 00:00:00 UTC
volume_mute
Correct Answer
Assess the impact of the proposed change on the existing requirements and project value.
Explanation
Before any change is approved or implemented, the BA must perform an impact analysis to understand how the change affects the solution scope, value, and other requirements.