A project sponsor demands that a new feature be added to a baselined project. What should the BA do FIRST?

publish date1969/12/31 00:00:00 UTC

volume_mute

Correct Answer

Assess the impact of the proposed change on the existing requirements and project value.

Explanation

Before any change is approved or implemented, the BA must perform an impact analysis to understand how the change affects the solution scope, value, and other requirements.