What is 'Requirement Prioritization' intended to achieve?
publish date: 1969/12/31 00:00:00 UTC
volume_mute
Correct Answer
To maximize the value delivered by the project within given constraints.
Explanation
Prioritization ensures that the most valuable and critical requirements are addressed first, optimizing the use of limited resources.
Reference