A BA identifies that a proposed design option will take 2 years to implement, but the business need is urgent (needed in 6 months). This design option is failing which check?https://go-math-science.com/computing/software-engineering/requirements-engineering/cbap-certification-practice-exams/cbap-practice-exam-8/a-ba-identifies-that-a-proposed-design-option-will-take-2-years-to-implement-but-the-business-need-is-urgent-needed-in-6-months-this-design-option-is-failing-which-checkhttps://go-math-science.com/@@site-logo/logo-new.png
volume_mute
A BA identifies that a proposed design option will take 2 years to implement, but the business need is urgent (needed in 6 months). This design option is failing which check?
publish date: 2026/04/27 21:04:11.681489 UTC
volume_mute
Correct Answer
Schedule Feasibility
Explanation
Schedule feasibility assesses whether the solution can be delivered within the required timeframe to meet the business need.