A BA is performing 'Requirements Validation.' What is the primary goal of this task?

publish date2026/04/27 21:04:8.218333 UTC

volume_mute

Correct Answer

To ensure the requirements deliver real business value and align with goals.

Explanation

Validation ensures the 'Right' things are being built—meaning the requirements accurately represent the business intent and provide value.

Reference