A BA is performing 'Analyze Potential Value and Recommend Solution'. Solution A has a Net Present Value (NPV) of 120,000 USD and a Benefit-Cost Ratio (BCR) of 1.8. Solution B has an NPV of 140,000 USD and a BCR of 1.4. Which solution should the BA recommend if the goal is absolute value?

publish date2026/03/08 05:59:11.445789 UTC

volume_mute

Correct Answer

Solution B

Explanation

NPV measures the absolute total valu ecreated by a project; thereforce, the solution with the highest NPV is preferred for absolute value.