A BA is performing 'Analyze Potential Value and Recommend Solution'. Solution A has a Net Present Value (NPV) of 120,000 USD and a Benefit-Cost Ratio (BCR) of 1.8. Solution B has an NPV of 140,000 USD and a BCR of 1.4. Which solution should the BA recommend if the goal is absolute value?https://go-math-science.com/computing/software-engineering/requirements-engineering/cbap-certification-practice-exams/cbap-practice-examp-2/a-ba-is-performing-analyze-potential-value-and-recommend-solution-solution-a-has-a-net-present-value-npv-of-120-000-usd-and-a-benefit-cost-ratio-bcr-of-1-8-solution-b-has-an-npv-of-140-000-usd-and-a-bcr-of-1-4-which-solution-should-the-ba-recommend-if-thehttps://go-math-science.com/@@site-logo/logo-new.png
volume_mute
A BA is performing 'Analyze Potential Value and Recommend Solution'. Solution A has a Net Present Value (NPV) of 120,000 USD and a Benefit-Cost Ratio (BCR) of 1.8. Solution B has an NPV of 140,000 USD and a BCR of 1.4. Which solution should the BA recommend if the goal is absolute value?
publish date: 2026/03/08 05:59:11.445789 UTC
volume_mute
Correct Answer
Solution B
Explanation
NPV measures the absolute total valu ecreated by a project; thereforce, the solution with the highest NPV is preferred for absolute value.