A project's 'Total Potential Value' is 1M. Due to 'Enterprise Limitations', only 80% of the value can be realized. If the cost to implement is 500k, what is the 'Expected Net Value'?https://go-math-science.com/computing/software-engineering/requirements-engineering/cbap-certification-practice-exams/cbap-practice-examp-2/a-projects-total-potential-value-is-1m-due-to-enterprise-limitations-only-80-of-the-value-can-be-realized-if-the-cost-to-implement-is-500k-what-is-the-expected-net-valuehttps://go-math-science.com/@@site-logo/logo-new.png
volume_mute
A project's 'Total Potential Value' is 1M. Due to 'Enterprise Limitations', only 80% of the value can be realized. If the cost to implement is 500k, what is the 'Expected Net Value'?
publish date: 2026/03/09 19:36:4.189234 UTC
volume_mute
Correct Answer
$300,000
Explanation
Realizable value = 1,000,000 * 0.80 = 800,000.
Net Value = Realizable Value - Cost = 800,000 - 500,000 = 300,000.