A stakeholder requests a change. The BA calculates that implementing the change will cost 5,000 but will save 10 hours of manual work per month. If the labor rate is 50/hour, what is the 'Break-even Point' in months?https://go-math-science.com/computing/software-engineering/requirements-engineering/cbap-certification-practice-exams/cbap-practice-examp-2/a-stakeholder-requests-a-change-the-ba-calculates-that-implementing-the-change-will-cost-5-000-but-will-save-10-hours-of-manual-work-per-month-if-the-labor-rate-is-50-hour-what-is-the-break-even-point-in-monthshttps://go-math-science.com/@@site-logo/logo-new.png
volume_mute
A stakeholder requests a change. The BA calculates that implementing the change will cost 5,000 but will save 10 hours of manual work per month. If the labor rate is 50/hour, what is the 'Break-even Point' in months?