In 'Business Analysis Planning and Monitoring', a BA chooses an 'Adaptive' approach. Which of the following mathematical concepts is most likely used for planning?

publish date2026/03/09 19:16:58.639905 UTC

volume_mute

Correct Answer

Velocity and Lead Time

Explanation

Adaptive (Agile) approaches rely on emirical data like velocity (output per iteration) and lead time to forecast future delivery.