Change Management Three Stages

publish date2026/06/06 23:20:12.796368 UTC

volume_mute
False
Please drag and drop the options to sort them

Sort the three stages of requirements change management in the correct order.

Problem Analysis and Change Specification
Change Analysis and Costing
Change Implementation

Correct Answer

(1) Problem Analysis and Change Specification
(2) Change Analysis and Costing
(3) Change Implementation

Explanation

The three change management stages in order: (1) Problem Analysis and Change Specification — validate the change proposal and refine it with the requestor; (2) Change Analysis and Costing — assess impact using traceability, estimate cost, and decide whether to proceed; (3) Change Implementation — modify the requirements document and, where necessary, the system design and implementation.

Reference

Software Engineering, Ian Sommerville, 9th edition