Problem Analysis and Change Specification
Change Analysis and Costing
Change Implementation
Correct Answer
(1) Problem Analysis and Change Specification
(2) Change Analysis and Costing
(3) Change Implementation
Explanation
The three change management stages in order: (1) Problem Analysis and Change Specification — validate the change proposal and refine it with the requestor; (2) Change Analysis and Costing — assess impact using traceability, estimate cost, and decide whether to proceed; (3) Change Implementation — modify the requirements document and, where necessary, the system design and implementation.
Reference
Software Engineering, Ian Sommerville, 9th edition