volume_mutePlease drag and drop the options to sort them
Sort the three principal stages of a requirements change management process in the correct order.
Problem Analysis and Change Specification
Change Analysis and Costing
Change Implementation
Correct Answer
(1) Problem Analysis and Change Specification
(2) Change Analysis and Costing
(3) Change Implementation
Explanation
The three stages in order: (1) Problem Analysis and Change Specification — validate the change proposal; (2) Change Analysis and Costing — assess impact and decide whether to proceed; (3) Change Implementation — modify the requirements document and, where necessary, the system design and implementation.