Three Stages of Change Management

publish date2026/06/06 22:28:7.505241 UTC

volume_mute
False
Please drag and drop the options to sort them

Sort the three principal stages of a requirements change management process in the correct order.

Problem Analysis and Change Specification
Change Analysis and Costing
Change Implementation

Correct Answer

(1) Problem Analysis and Change Specification
(2) Change Analysis and Costing
(3) Change Implementation

Explanation

The three stages in order: (1) Problem Analysis and Change Specification — validate the change proposal; (2) Change Analysis and Costing — assess impact and decide whether to proceed; (3) Change Implementation — modify the requirements document and, where necessary, the system design and implementation.

Identified Problem Problem Analysis and Change Specification Change Analysis and Costing Change Implementation Revised Requirements

Reference

Software Engineering, Ian Sommerville, 9th edition