Complete the sentence about how requirements are handled during incremental delivery.

Once an increment is under development, requirements changes for the (1) increment are not accepted. However, further requirements analysis for (2) increments can take place.

Please drag and drop the selected option in the right place or type it instead
current
later

Correct Answer

(1) current
(2) later

Explanation

Requirements changes for the current increment are not accepted once development has started — this preserves stability. However, further requirements analysis for later increments can continue to take place in parallel.

Reference

Software Engineering, Ian Sommerville, 9th edition