The waterfall model is often described as a plan-driven process.

What does it mean for the waterfall model to be plan-driven?

Correct Answer

All process activities are planned and scheduled before development begins.

Explanation

In a plan-driven process like the waterfall model, the major activities and their order are planned up front, and progress is measured against this plan.

Reference

Software Engineering, Ian Sommerville, 9th edition