Plan-driven nature of the waterfall model
publish date: 2026/05/28 22:08:31.019777 UTC
volume_mute
The waterfall model is often described as a plan-driven process.
What does it mean for the waterfall model to be plan-driven?
Correct Answer
All process activities are planned and scheduled before development begins.
Explanation
In a plan-driven process like the waterfall model, the major activities and their order are planned up front, and progress is measured against this plan.
Reference
Software Engineering, Ian Sommerville, 9th edition