Waterfall and risk of misfit
publish date: 2026/05/28 22:08:34.371414 UTC
volume_mute
Because requirements are fixed early in the waterfall model, there is a risk that the delivered system does not match user needs.
Which factor most contributes to this risk?
Correct Answer
Users may not fully understand their needs at the start of the project.
Explanation
Users often refine their understanding over time; freezing requirements early can lock in misunderstandings that are costly to correct later.
Reference
Software Engineering, Ian Sommerville, 9th edition