Unlike the waterfall model, the RUP does not equate phases directly with process activities. How are phases and activities related in the RUP?
Correct Answer
Phases in the RUP are more closely related to business concerns rather than technical activities — all workflows may be active across all phases
Explanation
Unlike the waterfall model where phases are equated with process activities, phases in the RUP are more closely related to business rather than technical concerns. Workflows are static technical activities that are not associated with a single phase — in principle, all workflows may be active at all stages of the process.
Reference
Software Engineering, Ian Sommerville, 9th edition