The CFO demands the project start immediately, but the Store Managers are entering their peak holiday season. Which 'Planning' decision should the BA recommend?

publish date2026/04/27 21:27:24.389531 UTC

volume_mute

Correct Answer

Adopt a 'Phased Approach,' starting with a pilot in the 5 lowest-volume stores during the holiday.

Explanation

This balances the 'Need' for change with the 'Enterprise Limitation' of peak season workload, reducing risk while still demonstrating progress (Plan BA Approach).

Reference