volume_mute

During an elicitation session, a BA notices that the stakeholders are using inconsistent terminology for the same process. What should the BA do FIRST?

publish date1969/12/31 00:00:00 UTC

volume_mute

Correct Answer

Document the different terms and create a Glossary.

Explanation

Creating a glossary or data dictionary ensures 'Understandability' and consistency across the enterprise and project stakeholders.

Reference

go-math-science.com


Quizzes you can take where this question appears