Stakeholders are in conflict over the priority of two requirements. What is the BEST way for the BA to facilitate a resolution?https://go-math-science.com/computing/software-engineering/requirements-engineering/cbap-certification-practice-exams/cbap-practice-exam-7/stakeholders-are-in-conflict-over-the-priority-of-two-requirements-what-is-the-best-way-for-the-ba-to-facilitate-a-resolutionhttps://go-math-science.com/@@site-logo/logo-new.png
volume_mute
Stakeholders are in conflict over the priority of two requirements. What is the BEST way for the BA to facilitate a resolution?
publish date: 1969/12/31 00:00:00 UTC
volume_mute
Correct Answer
Use objective criteria like NPV, risk, and regulatory compliance to re-evaluate priorities.
Explanation
Prioritization should be based on objective business value and risk factors rather than subjective opinions or ease of work.