Which of the following is a key element of the 'Approve Requirements' task?
publish date: 1969/12/31 00:00:00 UTC
volume_mute
Correct Answer
Defining the approval authority and process.
Explanation
Before requirements can be approved, the BA must establish who has the authority to sign off and what the process for approval entails.