A BA is calculating 'Cost of Quality'. Prevention costs are 10k, Appraisal costs are 5k, Internal Failure costs are 20k, and External Failure costs are 50k. What is the total 'Cost of Poor Quality' (CoPQ)?

publish date2026/03/09 19:27:23.219745 UTC

volume_mute

Correct Answer

$70,000

Explanation

CoPQ includes only the failure costs (Internal + External).

20,000 + 50,000 = 70,000.