An organization is performing 'Benchmarking'. Its 'Order Cycle Time' is 5 days. The industry leader's time is 2 days. What is the 'Benchmarking Gap' in days?https://go-math-science.com/computing/software-engineering/requirements-engineering/cbap-certification-practice-exams/cbap-practice-examp-2/an-organization-is-performing-benchmarking-its-order-cycle-time-is-5-days-the-industry-leaders-time-is-2-days-what-is-the-benchmarking-gap-in-dayshttps://go-math-science.com/@@site-logo/logo-new.png
volume_mute
An organization is performing 'Benchmarking'. Its 'Order Cycle Time' is 5 days. The industry leader's time is 2 days. What is the 'Benchmarking Gap' in days?
publish date: 2026/03/09 19:32:37.289617 UTC
volume_mute
Correct Answer
3 days
Explanation
The gap is the absolute difference between the current state performance and the benchmark targete: 5 - 2 = 3.