A project's 'Change Strategy' involves three transition states. Transition 1 provides 10k value, Transition 2 provides 20k, and the Future State provides 100k. If the project is canceled after Transition 2, what is the 'Sunk Cost' if total spend so far was 60k?https://go-math-science.com/computing/software-engineering/requirements-engineering/cbap-certification-practice-exams/cbap-practice-examp-2/a-projects-change-strategy-involves-three-transition-states-transition-1-provides-10k-value-transition-2-provides-20k-and-the-future-state-provides-100k-if-the-project-is-canceled-after-transition-2-what-is-the-sunk-cost-if-total-spend-so-far-was-60khttps://go-math-science.com/@@site-logo/logo-new.png
volume_mute
A project's 'Change Strategy' involves three transition states. Transition 1 provides 10k value, Transition 2 provides 20k, and the Future State provides 100k. If the project is canceled after Transition 2, what is the 'Sunk Cost' if total spend so far was 60k?
publish date: 2026/03/09 07:07:37.768550 UTC
volume_mute
Correct Answer
$60,000
Explanation
Sunk cost is the total amount already spent that cannot be recovered, regardless of the value achieved.