A BA is estimating the effort for a task using PERT (Program Evaluation and Review Technique). The Optimistic estimate is 4 days, the Most Likely is 7 days, and the Pessimistic is 16 days. What is the weighted average?https://go-math-science.com/computing/software-engineering/requirements-engineering/cbap-certification-practice-exams/cbap-practice-examp-2/a-ba-is-estimating-the-effort-for-a-task-using-pert-program-evaluation-and-review-technique-the-optimistic-estimate-is-4-days-the-most-likely-is-7-days-and-the-pessimistic-is-16-days-what-is-the-weighted-averagehttps://go-math-science.com/@@site-logo/logo-new.png
volume_mute
A BA is estimating the effort for a task using PERT (Program Evaluation and Review Technique). The Optimistic estimate is 4 days, the Most Likely is 7 days, and the Pessimistic is 16 days. What is the weighted average?