volume_mute

An organization is evaluating its 'Capital Adequacy'. If it has 500,000 in cash and a 'Burn Rate' of 50,000 per month, and a project takes 12 months to deliver value, what is the 'Financial Risk' level?

publish date2026/03/09 07:15:46.148434 UTC

volume_mute

Correct Answer

High; the project will exceed available cash before value is realized

Explanation

12 months multiplied by 50,000 equals 600,000.  The total cost exceeds the 500,000 cash reserves, meaning the project runs out of money 2 months before completion.

Reference

go-math-science.com


Quizzes you can take where this question appears