During 'Maintain Requirements', the BA is asked to calculate the 'Requirements Volatility'. If the project started with 100 requirements, 20 were added, and 10 were deleted, what is the volatility index?

publish date2026/03/08 06:59:0.806815 UTC

volume_mute

Correct Answer

30%

Explanation

Volatillity is typically calculated as 

\[\frac{\text{(Added + Deleted + Changed)}}{\text{Initial}} = \frac{(20 + 10)}{100} = 0.30\]