Diagram: overlapping increments
publish date: 2026/05/29 08:22:41.451210 UTC
volume_mute
The following diagram shows overlapping increments in development.
What does the overlap between increments represent?
Correct Answer
Work on a new increment can begin before the previous increment is fully completed.
Explanation
In practice, teams may start planning or developing the next increment while the current one is still being validated or refined.
Reference
Software Engineering, Ian Sommerville, 9th edition