How are the four basic process activities (specification, development, validation, and evolution) organized differently in the waterfall model versus incremental development?
Correct Answer
In waterfall they are organized in sequence; in incremental development they are interleaved
Explanation
The four basic process activities are organized differently in different development processes. In the waterfall model, they are organized in sequence, whereas in incremental development they are interleaved.
Reference
Software Engineering, Ian Sommerville, 9th edition