According to Sommerville, what is the major problem of the waterfall model?

Correct Answer

The inflexible partitioning of the project into distinct stages makes it difficult to respond to changing customer requirements

Explanation

The waterfall model's major problem is the inflexible partitioning of the project into distinct stages. Commitments must be made at an early stage in the process, which makes it difficult to respond to changing customer requirements.

Reference

Software Engineering, Ian Sommerville, 9th edition