Which of the following best describes how the waterfall model approaches planning and scheduling?
Correct Answer
It is a plan-driven process where all activities must be planned and scheduled before work begins
Explanation
The waterfall model is an example of a plan-driven process — in principle, you must plan and schedule all of the process activities before starting work on them.
Reference
Software Engineering, Ian Sommerville, 9th edition