A project moves from the design phase to the testing phase. The BA ensures that each test case can be mapped back to a specific functional requirement. This is an example of:

publish date2026/03/10 23:19:0.914162 UTC

volume_mute

Correct Answer

Backward Traceability

Explanation

Backward traceability ensures that every test case, design element, or deliverable can be traced back to its originating requirement. It answers the question:

“Why does this test case exist?”