A stakeholder requests a change that will significantly improve user experience but will delay the project by two weeks. What should the BA do first?

publish date2026/03/11 04:17:12.630873 UTC

volume_mute

Correct Answer

Assess the impact of the change

Explanation

Always assess impact before taking action on a change request.